The DEC typically mails out stormwater invoices in the late fall. If this is your first invoice, then expect to pay the State the following fees:
- $110 per acre of land disturbed (initial authorization fee – billed one time)
- $675 per acre of future impervious surface (initial authorization fee billed one time)
- An annual $110 regulatory fee (billed every year until a NOT is submitted)
Finished or almost finished with construction? Stabilize your construction sites now and file Notice of Terminations (NOTs) by December 31st to avoid paying next year’s $110 fee.
BME’s qualified SWPPP inspectors monitor construction sites, provide reporting, and manage required documentation and notifications.